The Grenfell Tower Inquiry

The Grenfell Tower Inquiry was set up to examine the circumstances leading up to and surrounding the tragic fire at Grenfell Tower on 14 June 2017. The public inquiry was formally set up on 15 August 2017.

The inquiry was separated into two phases and was chaired by Sir Martin Moore-Bick, a retired judge of the Court of Appeal of England and Wales.

Jump to:

Phase 1 

Phase 2

Phase 1

Phase 1 of the inquiry began on 21 May 2018 and concluded on 12 December the same year. This phase looked at the events on the night of the fire.

The inquiry published its Phase 1 report on 30 October 2019, drawing a number of conclusions and making a series of recommendations for building owners.

In particular, it concluded that:

  • The flames spread rapidly due to the presence of ACM panels with polyethylene cores.
  • That there is evidence to suggest that the external wall system used on Grenfell Tower was not compliant with building regulations.

The recommendations relate to:

  • Specific safety checks of buildings and equipment within buildings, such as lifts.
  • The provision of information to residents and local fire and rescue services.
  • Reviewing and maintaining fire safety mechanisms, evacuation procedures and ensuring the compliance of fire doors.

Following the publication of the phase one report, we produced a member briefing summarising the findings and the implications. Since then, the government has been implementing a programme of regulatory change that takes account of the inquiry’s recommendations.

As well as changes to the Fire Safety Order 2005, summarised on our Fire Safety Act webpage, the government has brought in the Fire Safety (England) Regulations, which commenced on 23 January 2023, which we have also summarised.

The Inquiry recommended that building owners and managers must provide PEEPs for residents who wouldn’t be able to evacuate independently in an emergency. Details on recent government announcements about PEEPs can be found above. 

Find out more on the Grenfell Tower Inquiry website

Phase 2

The government's response

The government accepted the findings of the report and committed to acting on all of the recommendations, 49 of which will be implemented in full. We have summarised key actions from the government's response below. 

Resident empowerment and quality standards

  • The government reaffirmed its commitment to implementing various standards including the Social Tenant Access to Information Requirements, a Competence and Conduct Standard, a new Decent Homes Standard and Minimum Energy Efficiency Standards. 
  • The Four Million Homes resident training programme and the Social Housing Resident Panel are being extended, and the government is taking forward the Make Things Right campaign.

Resident and building safety

  • The government reiterated its commitment to bringing forward regulations that would require Residential Personal Emergency Evacuation Plans.
  • The government accepts that a review of the definition of higher-risk buildings should take place and will set out plans for a further review in summer 2025.
  • Approved Document B, the guidance that supports the implementation of fire safety aspects of the building regulations, will be placed under continuous review, and the Building Safety Regulator will launch a consultation on further changes by autumn 2025.
  • The government will legislate to require social landlords to conduct electrical safety checks at least every five years and PAT tests on electrical appliances provided by landlords.

Competence

  • It will be mandatory for fire risk assessors to have their competence independently verified by a UK Accreditation Service body. 
  • The government will engage with a panel of experts in the field of fire engineering to consider what should be expected of a competent fire engineer.
  • The government accepts the recommendation that a licensing scheme be introduced for principal contractors wishing to work on higher-risk buildings and will consult with industry on how best to do this.

The construction industry

  • The government will take forward the recommendation for a single regulator with responsibility for construction and will consult on this in the autumn. However, it is proposed that the new regulator will not have responsibility for testing and certification of products or for issuing certificates of compliance, due to conflicts of interest. The regulator will have responsibility for investigating serious building safety incidents and this will be consulted upon in the autumn.
  • A new Chief Construction Adviser role will also be created, initially leading work with stakeholders to design the single regulator model and leading a process of shared responsibility with industry.
  • The government has published a construction products green paper, setting out proposals for system-wide reform of the construction products sector to address the systemic failures that contributed to the tragedy at Grenfell Tower.

Phase 2 summary and briefing

Phase 2 of the inquiry examined the cause of the fire, including how Grenfell Tower came to be in a condition that allowed the fire to spread in the way identified in phase one.

The inquiry’s Phase 2 report was published on 4 September 2024.

In concluded that the 72 deaths which occurred were avoidable and the residents were badly failed by those responsible for their safety. It highlighted the shortcomings of the council, the London Fire Brigade, successive governments, the Tenant Management Organisation (TMO) and the wider construction industry in particular.

It contained a number of recommendations including increased regulation of the construction industry, better training for fire and rescue services, and changes designed to improve fire safety management in existing buildings.

The report sets out the failings of Grenfell Tower’s Tenant Management Organisation (TMO) and the importance of learning from its failures, particularly around fire safety management. The panel has urged all those responsible for the management of social housing to give due consideration to the TMO’s shortcomings and take appropriate action. The panel stated that following the passing of the Social Housing Regulation Act, it did not consider it necessary to make any additional recommendations to address the failings of the TMO.

The panel reiterated its Phase 1 recommendation that Personal Emergency Evacuation Plans (PEEPs) are in place for residents who would not be able to evacuate independently in an emergency. Earlier this week the government announced that it would be bringing forward proposals to introduce Residential PEEPs for vulnerable and disabled residents. These proposals will apply to high-rise and higher-risk buildings and the government has committed funding to help social housing providers to deliver on this. We are seeking to understand more about the proposals and what the funding will be available for and will keep our members updated on any developments. 

We have produced a member briefing on Phase 2 of the inquiry, which summarises the parts of the report that are most relevant to housing associations.

Member only

Please login to access this member only content.

Who to speak to

Victoria Moffett, Head of Building and Fire Safety Programmes